8/23/11 Traffic Update for NID’s Banner Cascade Pipeline Project Construction


Construction on NID’s Banner Cascade Pipeline project continues on Banner Mountain during good weather conditions between 7:00 AM and 7:00 PM. 
Construction on Banner Lava Cap Road near Red Gate Road continues.  Residents should expect delays up to 20 minutes during construction activities; watch for flaggers to safely direct traffic.  Construction equipment will continue to use Red Gate Road to access the Overland section.  Residents should expect minimal delays on Red Gate Road during construction activities; delays may occasionally be up to twenty minutes.
Curb replacement to resume on Wednesday, August 24 on Idaho Maryland Road, between Lee Lane and Banner Lava Cap Road, and on Banner Lava Cap Road, between Idaho Maryland Road and Wings of Morning Drive.  Residents should expect delays up to 20 minutes during construction activities. Watch for flaggers to safely direct traffic through the construction zone.

Raw water pipeline installation will be completed on Oak Ridge Drive and Lola’s Echo Road this week.   Work will progress north onto Red Dog Cross Road starting Wednesday, August 24th.  Residents should expect delays up to 20 minutes during construction activities. Watch for flaggers to safely direct traffic through the construction zone.   NID is coordinating vehicle traffic in an effort to help families get to the bus stop and school on time; therefore vehicles travelling into town on Red Dog Cross Road will have an open lane until 8:00 AM.

 Raw water pipeline installation continues on Wings of Morning Drive and is expected to cross Clipper Creek Road Thursday, August 25th.   Residents should expect delays up to 20 minutes while the raw water pipeline installation crosses Clipper Creek Road.  Detours will be available without delays after construction crosses Clipper Creek Road.  The east end detour on Wings of Morning Drive is available for residential traffic as construction activities now block through use of the road. Construction equipment and trucks will enter and exit Wings of Morning Drive from both ends.  Turnouts are available along the alignment route allowing for passing residential traffic.

If you need further information, contact Hugh Gordon, Project Ombudsman, at (530) 263-4352, email: Hugh-lu@att.net, or visit our webpage at www.nidbannercascade.com

Notices:
Construction on Banner Lava Cap Road near Red Gate Road continues.  Residents should expect delays up to 20 minutes during construction activities; watch for flaggers to safely direct traffic.
Curb replacement to resume on Wednesday, August 24 on
Idaho Maryland Road and on Banner Lava Cap RoadResidents should expect delays up to 20 minutes during construction activities. Watch for flaggers to safely direct traffic through the construction zone. 
Emergency vehicles will be given immediate access.

Starting Wednesday, August 24th, work will progress from
Oak Ridge Drive and Lola’s Echo Road onto Red Dog Cross Road.

Residents should expect delays up to 20 minutes during construction activities. Watch for flaggers to safely direct traffic through the construction zone. Emergency vehicles will be given immediate access.

In an effort to help families get to the bus stop and school on
time, flaggers will have an open lane for vehicles travelling
into town until 8:00 AM.

Raw water pipeline installation is expected to cross Clipper Creek Road on
Thursday, August 25th.  Residents should expect delays up to 20 minutes; detours will be available on Wings of Morning Drive after
construction crosses the Clipper Creek Road intersection.
Emergency vehicles will be given immediate access.

Banner Cascade Pipeline Project Construction Schedule
8/22/11 to 9/16/11

Banner Lava Cap Road to Elizabeth George WTP:
·        Raw water pipeline installation continues.  Construction will continue to start at 8:00AM to allow school bus traffic to pass.  Residents should expect delays up to 20 minutes during construction activities.
Red Gate Road:
·        Raw water pipeline installation is completed on Red Gate Road.  Construction equipment will continue to use Red Gate Road to access the Overland section.  Residents should expect minimal delays during construction activities.
Overland from Madrone Forest Drive to Red Gate Road:
·        Work is expected to begin on the creek crossing this week.
Madrone Forest Drive: Final cleanup ongoing.  No delays anticipated.
Overland between Madrone Forest Drive and the airport: Completed.
Airport and Loma Rica Water Treatment Plant:  Raw water pipeline
installation is completed from Lee Lane to the Loma Rica WTP.  General cleanup to follow this week.
Lee Lane:   Curb replacement has been postponed due to neighborhood residents’ request; resume date to be determined.
Idaho Maryland Road, between Lee Lane and Banner Lava Cap Road:
·        Curb replacement to resume on Wednesday August 24.  Residents should expect delays up to 20 minutes during construction activities.
Banner Lava Cap Road, between Idaho Maryland Road and Wings of
Morning Drive:
·        Curb replacement to resume on Wednesday August 24.  Residents should expect delays up to 20 minutes during construction activities.
Wings of Morning Drive (WOMD):
·        Raw water pipeline installation will be at Clipper Creek Road starting on Thursday, August 25th.   Residents should expect delays up to 20 minutes while installation crosses Clipper Creek Road.  Detours will be available with no delays after construction crosses the road.
·        A dedicated water truck for the WOMD area will regularly apply dust control measures during construction activities throughout the day.
·        Construction equipment and trucks will enter and exit Wings of Morning Drive from the temporary access on the east end and the permanent access on the west end.  Turnouts are available along the alignment route allowing for passing residential traffic.
Opalite Way/Snow Mountain Flow Control/Overland:
·        Control building construction work is progressing.
·        Raw water pipeline installation on Overland is completed.
Red Dog Cross Road, Lola’s Echo Road, and Oak Ridge Road:
·        Raw water pipeline installation will be completed on Oak Ridge Drive and Lola’s Echo Road this week.   Work will progress north onto Red Dog Cross Road starting Wednesday, August 24th.  Residents should expect delays up to 20 minutes during construction activities. 