Construction on NID’s Banner Cascade Pipeline project continues on Banner Mountain. Curb installation will be underway on Banner Lava Cap Road, Idaho Maryland Road, and Lee Lane 12/13 through 12/17, weather dependent; traffic will be limited to one lane with possible delays up to twenty minutes. Watch for construction signage and flaggers as they help safely direct traffic through the construction zones.
If you need further information, contact Hugh Gordon, Project Ombudsman, at (530) 263-4352 or email: Hugh-lu@att.net
Curbs will be installed on
Banner Lava Cap Road, Idaho Maryland Road, and Lee Lane
on December 13 through 17 if weather conditions allow.
Flaggers will be on site to safely direct traffic. Emergency vehicles will be given immediate access.
Thank you for being patient.
Banner Cascade Pipeline Project Construction Schedule 12/13/10 to 1/5/11
Due to the holidays, the next update will be available on January 6th, 2011. Construction activities will proceed as per this schedule, weather dependent.
■ Madrone Forest Drive:
· Finalizing culvert installation; no traffic delays are expected.
· Final clean-up is in progress.
· Phase one of restoration, soil stabilization, is completed; the contractor will maintain slopes through the winter. Phase two of restoration, tree and vegetation replanting, will be scheduled for the fall of 2011.
■ Overland between Madrone Forest Drive and the airport:
· Phase one of restoration, soil stabilization, is completed; the contractor will maintain slopes through the winter. Phase two of restoration, vegetation replanting, will be scheduled for later this fall.
■ Airport & Loma Rica Water Treatment Plant:
· Final clean-up along pipeline route is underway.
· Loma Rica Water Treatment Plant structures being constructed.
■ Lee Lane:
· Curb installation to occur 12/13 to 12/17, weather dependent; traffic will be limited to one lane with possible delays up to twenty minutes. The final lift of pavement will be installed in spring of 2011.
· Testing of the 48” raw water pipeline will resume in the spring.
· Tie-in to Idaho Maryland Road to be scheduled.
■ Idaho Maryland Road, between Lee Lane and Banner Lava Cap Road:
· Curb installation to occur 12/13 to 12/17, weather dependent; traffic will be limited to one lane with possible delays up to twenty minutes. The final lift of pavement will be installed in spring of 2011.
· The contractor is waiting for weather conditions to improve in order to install the treated water pipeline.
· Testing of the 48” raw water pipeline will resume in the spring.
· Tie-in to Lee Lane to be scheduled.
· Phase one of restoration, soil stabilization, is underway; the contractor will maintain slopes through the winter. Phase two of restoration, tree and vegetation replanting, will be scheduled for the fall of 2011.
■ Banner Lava Cap Road, between Idaho Maryland Road and Wings of Morning
Drive:
· Curb installation to occur 12/13 to 12/17, weather dependent; traffic will be limited to one lane with possible delays up to twenty minutes. The final lift of pavement will be installed in spring of 2011.
- Testing of the 48” raw water pipeline is being prepared.
· The contractor is waiting for weather conditions to improve in order to start on vault construction.
Construction Scheduled to Begin in 2011
■ Wings of Morning Drive
■ Opalite Way
■ Red Dog Cross Road
■ Clipper Creek Siphon
■ Overland from Madrone Forest Drive to Red Gate Road
■ Red Gate Road
■ Banner Lava Cap Road