Wednesday, July 20, 2011

NID public meeting Aug 11 5pm

NID is hosting an informal open-forum public information meeting for residents along the construction route and others impacted by the construction. The August 11 meeting will be held at NID’s project trailers at the intersection of Idaho Maryland Road and Banner Lava Cap Road from 5:00 to 6:30 PM.  This meeting is intended to answer residents’ questions and clarify details of the project. Please plan on attending if you have questions.
If you need further information, contact Hugh Gordon, Project Ombudsman, at (530) 263-4352, email: Hugh-lu@att.net, or visit our webpage at www.nidbannercascade.com.  

7/19/11 Traffic Update for NID’s Banner Cascade Pipeline Project Construction

Construction on NID’s Banner Cascade Pipeline project continues on Banner Mountain during good weather conditions between 7:00 AM and 7:00 PM.  Raw water pipeline installation continues on Wings of Morning Drive east of Sesame Street. The east end detour on Wings of Morning Drive will be available for residential traffic as construction activities now block through use of the road. Construction equipment and trucks will enter and exit Wings of Morning Drive from both ends.  Turnouts are available along the alignment route allowing for passing residential traffic. No traffic delays are anticipated.
Work is nearly complete on Banner Lava Cap Road, Idaho Maryland Road, and Lee Lane.  Expect delays to be minimal while general cleanup is underway this week; however delays may rarely be up to twenty minutes in duration.  Flaggers will safely direct traffic through the construction zones; watch for signage.
Raw water pipeline installation is underway on the Thomas Ranch at the end of Red Gate Road.  Expect construction equipment and truck traffic on Red Gate Road and Banner Lava Cap Road heading toward Old Tunnel Road.
If you need further information, contact Hugh Gordon, Project Ombudsman, at (530) 263-4352, email: Hugh-lu@att.net, or visit our webpage at www.nidbannercascade.com
Notices:
NID is hosting an informal open-forum public information meeting for residents along the construction route and others impacted by the construction.
The August 11 meeting will be held at NID’s project trailers at the intersection of Idaho Maryland Road and Banner Lava Cap Road from 5:00 to 6:30 PM. 
This meeting is intended to answer residents’ questions and clarify details of the project.
Please plan on attending if you have questions.

The east end detour on Wings of Morning Drive will be
available for residential traffic as construction activities will now
block through use of the road.  Construction equipment and
trucks will enter and exit Wings of Morning Drive from both
ends from now until the project is completed.  Turnouts are available
along the alignment route allowing for passing residential traffic.
No traffic delays are anticipated.

General clean up on Banner Lava Cap Road, Idaho Maryland Road,
and Lee Lane continues. Minimal delays are expected, however
they may be up to twenty minutes in duration.

Flaggers will safely direct traffic through the construction zones. Emergency vehicles will be given immediate access. Thank you for being patient.

Banner Cascade Pipeline Project Construction Schedule
7/18/11 to 8/12/11
NID is hosting an informal open-forum public information meeting for
residents along the construction route and others impacted by the construction. The August 11 meeting will be held at NID’s project trailers at the intersection
of Idaho Maryland Road and Banner Lava Cap Road from 5:00 to 6:30 PM.  This meeting is intended to answer residents’ questions and clarify details
of the project. Please plan on attending if you have questions.
Banner Lava Cap Road to Elizabeth George WTP:
·        Raw water pipeline installation will begin after Red Gate Road is completed. The information board at the intersection of Red Gate Road and Banner Lava Cap Road will be installed soon. 
Red Gate Road:
·        Staging of materials will begin this week. 
·        Raw water pipeline installation will start within the next three weeks after Overland from Madrone Forest Drive to Red Gate Road section is completed. The information board at the intersection of Red Gate Road and Banner Lava Cap Road will be installed soon. 
Overland from Madrone Forest Drive to Red Gate Road:
·        Raw water pipeline installation on the Thomas Ranch begins on July 18.
·        Logging, clearing, and stump grinding Overland from Madrone Forest Drive to the Thomas Ranch is being scheduled to start within the next three weeks.
Madrone Forest Drive: Final cleanup ongoing.  No delays anticipated.
Overland between Madrone Forest Drive and the airport: Completed.
Airport and Loma Rica Water Treatment Plant: Construction is ongoing.
Lee Lane:
·        Final cleanup ongoing.  No delays anticipated.
·        Curb replacement to be scheduled in the next few weeks.
Idaho Maryland Road, between Lee Lane and Banner Lava Cap Road:
·        General cleanup will continue this week; expect minimal delays.
·        Curb replacement and road striping to be scheduled in the next few weeks.
Banner Lava Cap Road, between Idaho Maryland Road and Wings of
Morning Drive:
·        General cleanup will continue this week; expect minimal delays.
·        Curb replacement and road striping to be scheduled in the next few weeks.
Wings of Morning Drive (WOMD):
·        Raw water pipeline installation has reached the paved section of WOMD; the east end of WOMD will be available for residential traffic. 
·        A dedicated water truck for the WOMD area will regularly apply dust control measures during construction activities throughout the day.
·        Construction equipment and trucks will enter and exit Wings of Morning Drive from both ends.  Turnouts are available along the alignment route allowing for passing residential traffic.
Opalite Way/Snow Mountain Flow Control/Overland:
·        Control building construction work is progressing.
Red Dog Cross Road, Lola’s Echo Road, and Oak Ridge Road:
·         Pipeline installation on Oak Ridge Road to begin next week.  

Friday, July 15, 2011

7/12/11 Traffic Update for NID’s Banner Cascade Pipeline Project Construction

Construction on NID’s Banner Cascade Pipeline project continues on Banner Mountain during good weather conditions between 7:00 AM and 7:00 PM.  Raw water pipeline installation continues on Wings of Morning Drive east of Sesame Street. The east end detour on Wings of Morning Drive will be available for residential traffic as construction activities now block through use of the road. Construction equipment and trucks will enter and exit Wings of Morning Drive from both ends.  Turnouts are available along the alignment route allowing for passing residential traffic. No traffic delays are anticipated.
Work is nearly complete on Banner Lava Cap Road, Idaho Maryland Road, and Lee Lane; expect minimal delays while general cleanup is underway this week.  Flaggers will safely direct traffic through the construction zones; watch for signage.
If you need further information, contact Hugh Gordon, Project Ombudsman, at (530) 263-4352, email: Hugh-lu@att.net, or visit our webpage at www.nidbannercascade.com

Notices:
The east end detour on Wings of Morning Drive will be
available for residential traffic as construction activities will now
block through use of the road.  Construction equipment and
trucks will enter and exit Wings of Morning Drive from both
ends from now until the project is completed.  Turnouts are available
along the alignment route allowing for passing residential traffic.
No traffic delays are anticipated.

General clean up on Banner Lava Cap Road, Idaho Maryland Road,
and Lee Lane continues. Minimal delays are expected, however
they may be up to twenty minutes in duration.

Flaggers will safely direct traffic through the construction zones. Emergency vehicles will be given immediate access. Thank you for being patient.

Banner Cascade Pipeline Project Construction Schedule
7/11/11 to 8/5/11

Banner Lava Cap Rd to E. George WTP: To be determined.
Red Gate Road: To be determined.
Overland from Madrone Forest Drive to Red Gate Road:
·        Tree removal and stump grinding is complete on the Thomas Ranch.  Material staging is scheduled for next week.
Madrone Forest Drive: Final cleanup this week.  No delays anticipated.
Overland between Madrone Forest Drive and the airport: Completed.
Airport and Loma Rica Water Treatment Plant: Construction is ongoing.
Lee Lane:
·        Treated water is now available for residents adjacent to the alignment; contact NID Customer Service at 530-273-6185 for information. 
·        General cleanup will continue this week; expect minimal delays.
·        Raw water pipeline installation across SWROA lot 3 toward the airport will begin this week.  All construction activity will now progress from the Airport side.  Fuel and worker trucks may access SWROA lot 3 from Lee Lane, but will not cross onto Airport property.
·        Curb replacement to be scheduled in the next few weeks.
Idaho Maryland Road, between Lee Lane and Banner Lava Cap Road:
·        Treated water is now available for residents adjacent to the alignment; contact NID Customer Service at 530-273-6185 for information. 
·        General cleanup will continue this week; expect minimal delays.
·        Curb replacement to be scheduled in the next few weeks.
Banner Lava Cap Road, between Idaho Maryland Road and Wings of
Morning Drive:
·        General cleanup will continue this week; expect minimal delays.
·        Curb replacement to be scheduled in the next few weeks.
Wings of Morning Drive (WOMD):
·        Raw water pipeline installation will reach paved section of WOMD this week; the east end of WOMD will be available for residential traffic. 
·        A dedicated water truck for the WOMD area will regularly apply dust control measures during construction activities throughout the day.
·        Construction equipment and trucks will enter and exit Wings of Morning Drive from both ends.  Turnouts are available along the alignment route allowing for passing residential traffic.
Opalite Way/Snow Mountain Flow Control/Overland:
·        Control building construction work is progressing.
Red Dog Cross Road, Lola’s Echo Road, and Oak Ridge Road:
·         Pipeline installation is scheduled for July.  Advanced notice of the construction start date will be given.  

Friday, July 8, 2011

Paving Done More to come

Final paving is completed on Lee Lane, Idaho Maryland Road, and Banner Lava Cap Road.  Work on jack-hammering out the manhole and valve box covers will take place on Monday, Tuesday, and Wednesday.  There will be a flagger at each location, with minimal delays anticipated. Final paving on the curbs is still to be scheduled, but is anticipated within the next few weeks.  Thank you for your patience with the project.

Wednesday, July 6, 2011

Reminder - Paving Thursday and Friday

Just a reminder that Teichert will be paving Thursday, 7/7, and Friday, 7/8, on Lee Lane, Idaho Maryland Road, and Banner Lava Cap Road.  Work will be underway from 7:00 AM until 7:00 PM. Expect delays of twenty minutes.  Use alternate routes if possible.  Curbs will not be repaired tomorrow; that work will take place in a few weeks.