Wednesday, December 15, 2010

Traffic Update for NID’s Banner Cascade Pipeline Project Construction

Construction on NID’s Banner Cascade Pipeline project continues on Banner Mountain.  Curb installation will be underway on Banner Lava Cap Road, Idaho Maryland Road, and Lee Lane 12/13 through 12/17, weather dependent; traffic will be limited to one lane with possible delays up to twenty minutes.  Watch for construction signage and flaggers as they help safely direct traffic through the construction zones. 

If you need further information, contact Hugh Gordon, Project Ombudsman, at (530) 263-4352 or email: Hugh-lu@att.net

Curbs will be installed on

Banner Lava Cap Road, Idaho Maryland Road, and Lee Lane

on December 13 through 17 if weather conditions allow.

Flaggers will be on site to safely direct traffic.  Emergency vehicles will be given immediate access.
Thank you for being patient.


Banner Cascade Pipeline Project Construction Schedule 12/13/10 to 1/5/11
Due to the holidays, the next update will be available on January 6th, 2011.  Construction activities will proceed as per this schedule, weather dependent.
Madrone Forest Drive: 
·        Finalizing culvert installation; no traffic delays are expected.
·        Final clean-up is in progress.
·        Phase one of restoration, soil stabilization, is completed; the contractor will maintain slopes through the winter.  Phase two of restoration, tree and vegetation replanting, will be scheduled for the fall of 2011.
Overland between Madrone Forest Drive and the airport: 
·        Phase one of restoration, soil stabilization, is completed; the contractor will maintain slopes through the winter.  Phase two of restoration, vegetation replanting, will be scheduled for later this fall.
Airport & Loma Rica Water Treatment Plant: 
·        Final clean-up along pipeline route is underway.
·        Loma Rica Water Treatment Plant structures being constructed.
Lee Lane: 
·        Curb installation to occur 12/13 to 12/17, weather dependent; traffic will be limited to one lane with possible delays up to twenty minutes.  The final lift of pavement will be installed in spring of 2011.
·        Testing of the 48” raw water pipeline will resume in the spring.
·        Tie-in to Idaho Maryland Road to be scheduled.
Idaho Maryland Road, between Lee Lane and Banner Lava Cap Road: 
·        Curb installation to occur 12/13 to 12/17, weather dependent; traffic will be limited to one lane with possible delays up to twenty minutes.  The final lift of pavement will be installed in spring of 2011.
·        The contractor is waiting for weather conditions to improve in order to install the treated water pipeline.
·        Testing of the 48” raw water pipeline will resume in the spring.
·        Tie-in to Lee Lane to be scheduled.
·        Phase one of restoration, soil stabilization, is underway; the contractor will maintain slopes through the winter.  Phase two of restoration, tree and vegetation replanting, will be scheduled for the fall of 2011.
Banner Lava Cap Road, between Idaho Maryland Road and Wings of Morning
    Drive: 
·        Curb installation to occur 12/13 to 12/17, weather dependent; traffic will be limited to one lane with possible delays up to twenty minutes.  The final lift of pavement will be installed in spring of 2011.
  • Testing of the 48” raw water pipeline is being prepared.
·        The contractor is waiting for weather conditions to improve in order to start on vault construction.
Construction Scheduled to Begin in 2011
Wings of Morning Drive
Opalite Way
Red Dog Cross Road
Clipper Creek Siphon
Overland from Madrone Forest Drive to Red Gate Road
Red Gate Road
Banner Lava Cap Road

Wednesday, December 8, 2010

Dec 17 Traffic Update

Construction on NID’s Banner Cascade Pipeline project continues on Banner Mountain.  Testing on Banner Lava Cap Road, Idaho Maryland Road, and Lee Lane is being prepared and taking place inside the 48” raw water pipeline. Traffic will be minimally affected, if at all; no delays are expected to occur.  Curb installation will be underway on Banner Lava Cap Road, Idaho Maryland Road, and Lee Lane 12/13 and 14, weather dependent; traffic will be limited to one lane with possible delays up to twenty minutes.  Watch for construction signage and flaggers as they help safely direct traffic through the construction zones. 

If you need further information, contact Hugh Gordon, Project Ombudsman, at (530) 263-4352 or email: Hugh-lu@att.net


Notice
Curbs will be installed on

Banner Lava Cap Road, Idaho Maryland Road, and Lee Lane

on December 13 and 14 if weather conditions allow.

Flaggers will be on site to safely direct traffic. 
Emergency vehicles will be given immediate access.
Thank you for being patient.


Banner Cascade Pipeline Project Construction Schedule 12/6/10 to 12/24/10
Madrone Forest Drive: 
·        Finalizing culvert installation; no traffic delays are expected.
·        Final clean-up is in progress.
·        Phase one of restoration, soil stabilization, is completed; the contractor will maintain slopes through the winter.  Phase two of restoration, tree and vegetation replanting, will be scheduled for the fall of 2011.
Overland between Madrone Forest Drive and the airport: 
·        Phase one of restoration, soil stabilization, is completed; the contractor will maintain slopes through the winter.  Phase two of restoration, vegetation replanting, will be scheduled for later this fall.
Airport & Loma Rica Water Treatment Plant: 
·        Final clean-up along pipeline route is underway.
·        Loma Rica Water Treatment Plant structures being constructed.
Lee Lane: 
·        Curbs are to be installed on 12/13 and 14, weather dependent; traffic will be limited to one lane with possible delays up to twenty minutes.  The final lift of pavement will be installed in spring of 2011.
·        Testing of the 48” raw water pipeline is underway.
·        Tie-in to Idaho Maryland Road to be scheduled.
Idaho Maryland Road, between Lee Lane and Banner Lava Cap Road: 
·        Curbs are to be installed on 12/13 and 14, weather dependent; traffic will be limited to one lane with possible delays up to twenty minutes.  The final lift of pavement will be installed in spring of 2011.
·        The contractor is waiting for weather conditions to improve in order to install the treated water pipeline.
·        Testing of the 48” raw water pipeline is underway.
·        Tie-in to Lee Lane to be scheduled.
·        Phase one of restoration, soil stabilization, is underway; the contractor will maintain slopes through the winter.  Phase two of restoration, tree and vegetation replanting, will be scheduled for the fall of 2011.
Banner Lava Cap Road, between Idaho Maryland Road and Wings of Morning
    Drive: 
·        Curbs are to be installed on 12/13 and 14, weather dependent; traffic will be limited to one lane with possible delays up to twenty minutes.  The final lift of pavement will be installed in spring of 2011.
  • Testing of the 48” raw water pipeline is being prepared and begun.
·        The contractor is waiting for weather conditions to improve in order to start on vault construction.
Construction Scheduled to Begin in 2011
Wings of Morning Drive
Opalite Way
Red Dog Cross Road
Clipper Creek Siphon
Overland from Madrone Forest Drive to Red Gate Road
Red Gate Road
Banner Lava Cap Road

Wednesday, November 17, 2010

Nov 16 Traffic Update

Construction on NID’s Banner Cascade Pipeline project continues on Banner Mountain .  Work continues on both Lee Lane and Idaho Maryland Road .  Paving operations will be underway on Lee Lane 11/17 and on Idaho Maryland Road between St. Ledger Forest Road and Lee Lane 11/17 and 18.  Expect delays up to 20 minutes; watch for construction signage and flaggers as they help safely direct traffic through the construction zones.  To avoid waiting in construction traffic on Idaho Maryland Road , use Old Tunnel Road between Banner Lava Cap Road and Brunswick Road .

If you need further information, contact Hugh Gordon, Project Ombudsman, at (530) 263-4352 or email: Hugh-lu@att.net

Notice:

The first lift of pavement will be installed on

Idaho Maryland Road and Lee Lane

on November 17 and 18 with curbs to follow on November 23 and 24.

Flaggers will be on site to safely direct traffic. 
Emergency vehicles will be given immediate access.
Thank you for being patient.


Banner Cascade Pipeline Project Construction Schedule 11/15/10 to 12/10/10
Madrone Forest Drive
·        Final clean-up is in progress.
·        Phase one of restoration, soil stabilization, is completed; the contractor will maintain slopes through the winter.  Phase two of restoration, tree and vegetation replanting, will be scheduled for the fall of 2011.
Overland between Madrone Forest Drive and the airport: 
·        Phase one of restoration, soil stabilization, is completed; the contractor will maintain slopes through the winter.  Phase two of restoration, vegetation replanting, will be scheduled for later this fall.
Airport & Loma Rica Water Treatment Plant: 
·        Final clean-up along pipeline route is underway.
·        Loma Rica Water Treatment Plant structures being constructed.
Lee Lane: 
·        The treated water pipeline installation, services, and vaults are completed.  Treated water may be available along the alignment later this year, weather dependent; call NID’s customer service for more information at 530-273-6185 .
·        General clean-up and preparations for paving are ongoing.  Flaggers will direct you through the construction as quickly as safety allows.  Thank you for your patience.  The first lift of pavement is scheduled to be installed on 11/17 and 18; curbs are scheduled for installation on 11/23 and 24.  The final lift of pavement will be installed in spring of 2011.
·        48” raw water pipeline testing and tie-in to Idaho Maryland Road to be scheduled.
Idaho Maryland Road, between Lee Lane and Banner Lava Cap Road : 
·        48” raw water pipeline installation is complete.  The treated water pipeline will start on 11/29 if weather conditions allow.  Flaggers will get you through the construction as quickly as safety allows. 
·        48” raw water pipeline testing and tie-in to Lee Lane to be scheduled.
·        Phase one of restoration, soil stabilization, is underway; the contractor will maintain slopes through the winter.  Phase two of restoration, tree and vegetation replanting, will be scheduled for the fall of 2011.
·        The first lift of pavement will be installed 11/18 in readiness for winter; curbs are scheduled for installation on 11/23 and 24.  The final lift of pavement will be installed in spring of 2011.
Banner Lava Cap Road, between Idaho Maryland Road and Wings of Morning
    Drive: 
·        Curbs are scheduled for installation on 11/23 and 24.
·        Vault construction is ongoing, and may be delayed until next year.

Construction Scheduled to Begin in 2011
Wings of Morning Drive
Opalite Way
Red Dog Cross Road
Clipper Creek Siphon
Overland from Madrone Forest Drive to Red Gate Road
Red Gate Road
Banner Lava Cap Road

Monday, November 15, 2010

Public Meeting – Tuesday, November 16, 2010 ; 6:30 – 8:00 p.m.

Public Meeting – Tuesday, November 16, 2010 ; 6:30 – 8:00 p.m.
Nevada County Horsemen Club
10600 Bubbling Wells Road (& Brunswick Road ), Grass Valley

Re: Banner Cascade Pipeline Project – Restoration Specifications

Dear Property Owner/Resident:

As part of our restoration for the Banner Cascade Pipeline Project, the District plans on replacing trees and landscaping that are affected by the construction.

You are invited to a meeting to discuss our approach for tree and vegetation restoration that will be held on Tuesday, November 16, 2010 , from 6:30 p.m. to 8:00 p.m., at the Nevada County Horsemen Club located at Bubbling Wells Road and Brunswick Road .

This meeting will be similar to previous workshops in that it will be an informal open house which will give property owners an opportunity to review the restoration plans and specifications and provide input and/or get clarification from the District.

We have also attached these specifications and plans to this letter for your information and review.

Sincerely,

Adrian Schneider, P.E.
Senior Project Engineer

Wednesday, October 27, 2010

Mud flow from storm damages Wolf Creek

Thanks to a resident who contacted Wolf Creek Community Alliance, WCCA and BMHA are going to meet with NID on Friday Oct 29 at 3PM at NID Office in Grass Valley to discuss keeping the project from further damaging Wolf Creek.  All residents are invited to attend.  Photos are below. 





Monday, October 18, 2010

NID Response relative to MMRP issues

1.    Medically fragile people not identified prior to construction starting on Madrone Forest
Ø  The ombudspersons are notifying property owners by phone or written notices and sometimes both when the construction will be within 500 feet of a residence.  The ombudspersons are asking if there are any medical issues that we should be aware of when this call is made.  If there is an issue with the property owners, NID will put the property owner in a local hotel while the construction is in front of their house.

2.    Construction workers personal vehicles parked in resident areas
Ø  This happened the first two days of the construction and has not happened since.

3.    Construction vehicles belching smoke
Ø  All of Teichert’s construction equipment operates under the new California Air Resources Board Tier III regulations for particulate emissions.

4.      Kids walking alone through construction zone.
Ø  All of the flagmen and inspectors are trained that if kids or adults walk up to the construction zone, these people need to be escorted through the work area by a member of the construction team.

5.      Trucks parking in school bus loading zone.
Ø  A couple of trucks were parked in front of the mail boxes for a short time before they were to be loaded on Banner Lava Cap. The contractor told them to move as soon as they were spotted.  We do not believe that this has happened when a school bus arrived.  Please note that school buses can stop anywhere and that all traffic is directed to stop when children will be crossing the street.

6.      Excess dust making it impractical to open windows on hot days and affecting solar panels
Ø  There was more dust than currently in the first couple of days of construction. Adjustments were made in procedures to deal with varying conditions to reduce dust.

7.      Lack of a fire plan
Ø  Nevada County Consolidated reviewed and accepted the fire protection plan submitted by Teichert at the beginning of this project.

8.    Lack of reconstruction plan prior to start of construction – what is the plan and timeline for reconstructing slopes on banner? Will it be done before it starts raining? When will the gravel be cleaned up?
Ø  The Banner Cascade Project has numerous restoration segments that have been completed.
1)    All trees have been identified within the pipe area. Trees that are to be removed as part of the project have been identified to the landowners, either at public meeting or during one on one meetings. Numerous trees have been avoided during design.
2)    Prior to construction, video and photographs were taken to confirm existing conditions of the road and private property along the alignment.
3)    Adjustments have been made in Right of Way Agreements to deal with special landscape issues.
4)    Our current contract with Teichert includes installation of erosion control such as jute netting and reseeding of all areas.
5)    We have contracted a tree specialist and a plant expert for consultation relating to the plant and tree restoration.
6)    We are in the process of finishing a restoration contract for the plant and tree restoration and expect to have it ready for review in two weeks.
7)   We are also working on a contract with a tree farm in Oregon to grow and ship all of the trees for this project.

9.      Missing pre-meetings to provide community with overview of project, and notices of what is about to happen are not being provided proactively (telephone poles being moved, roads being closed for part of or for an entire day, etc.)
Ø  We have had numerous public meetings to review the design drawings and one on one meetings with property owners to review the pipeline location and how the pipe would be installed.  
Ø  We plan to have a meeting with the individuals of the community as a group prior to construction in the Wings of Morning area and other areas. These meetings will discuss the construction plan and logistics of the traffic patterns and other issues during the installation of the pipeline.

10. Excessive noise from Jackhammers
Ø  Unfortunately, there will be noise generated from the construction of this project.  According to the MMRP, the contractor is allowed to perform their duties between the hours of 7a.m. and 7p.m. The contractor has in a couple of instances gone beyond this time during cleanup in efforts to provide a highest possible level of clean up for the day.  In some cases there will be jack hammers, excavators, and trucks operating during these working hours.  The contractor is trying to install the pipe as quickly as possible and the work in front of any individual residence will be temporary in nature.

Thursday, October 7, 2010

Construction Banner Lava Cap Saturday Oct 9

NID will be working on Saturday 10/9/10 along Banner Lava Cap Road between the two Altair Drive intersections.  They will be constructing a vault, tying into the treated water pipeline, and working on other services.  One lane will remain open with flaggers directing traffic from 7:00 AM to 5:00 PM .  Delays up to twenty minutes are expected. Use an alternate route if possible. 

Tuesday, October 5, 2010

Traffic Update

Traffic Update for NID’s Banner Cascade Pipeline Project Construction

Construction on NID’s Banner Cascade Pipeline project continues on Banner Mountain .  Construction is currently taking place on Banner Lava Cap Road, Idaho Maryland Road, and on Lee Lane .  Expect 20 minute delays while watching for construction signage and flaggers as they help safely direct traffic through the construction zones. 

 If you need further information, contact Hugh Gordon, Project Ombudsman, at (530) 263-4352 or email: Hugh-lu@att.net


Notices:
Phase one of restoration, soil stabilization, has begun on

Banner Lava Cap Road

EXPECT TRAFFIC DELAYS UP TO TWENTY MINUTES!
Flaggers will be on site to safely direct traffic. 
Emergency vehicles will be given immediate access.
If possible, use alternate routes. Thank you for being patient.


Pipeline installation to begin on

Idaho Maryland Road

between Banner Lava Cap Road and Lee Lane .  Pipeline installation continues on

Lee Lane.

EXPECT TRAFFIC DELAYS UP TO TWENTY MINUTES!
Flaggers will be on site to safely direct traffic.  Emergency vehicles will be given immediate access.
 If possible, use alternate routes. Thank you for being patient.



Banner Cascade Pipeline Project Construction Schedule 10/4/10 to 10/29/10
Madrone Forest Drive
  • Pipeline testing is underway.
  • Final asphalt paving will be scheduled soon.
  • Phase one of restoration, soil stabilization, will begin after the final pavement has been completed.  Phase two of restoration, vegetation replanting, will be scheduled shortly thereafter.
  • Please continue to drive slowly on the gravel roadway. 
Overland between Madrone Forest Drive and the airport: 
  • Installation of the 36” raw water pipeline on the Overland section is completed. Testing and general clean up is underway.
  • Phase one of restoration, soil stabilization, has begun.  Phase two of restoration, vegetation replanting, will be scheduled for later this Fall.
Airport & Loma Rica Water Treatment Plant: 
·        Pipeline testing is in progress.
·        Final clean-up along pipeline route is underway.
·        Loma Rica Water Treatment Plant structures being constructed.
Lee Lane: 
  • 48” raw water pipeline installation continues. The treated water pipeline will follow.  Flaggers will get you through the construction as quickly as safety allows.  Thank you for your patience.
Idaho Maryland Road, between Lee Lane and Banner Lava Cap Road : 
·                    48” raw water pipeline installation will begin as soon as the Banner Lava Cap section is completed; expect construction to begin shortly.  The treated water pipeline will follow.  Flaggers will get you through the construction as quickly as safety allows.  Thank you for your patience.
Banner Lava Cap Road, between Idaho Maryland Road and Wings of
     Moring Drive: 
  • Installation of the treated water pipeline on Banner Lava Cap Road between the two Altair Drives is nearly completed.  Pipeline testing will begin shortly.
  • Phase one of restoration, soil stabilization, is underway.  Phase two of restoration, vegetation replanting, will be scheduled shortly thereafter.

Construction Scheduled to Begin in 2011
Wings of Morning Drive
Opalite Way
Red Dog Cross Road
Clipper Creek Siphon
Overland from Madrone Forest Drive to Red Gate Road
Red Gate Road
Banner Lava Cap Road to E. George Water Treatment Plant

Saturday, October 2, 2010

Saturday 10/2 Construction

Got this yesterday.

There will be Saturday construction 10/2/10 on Banner Lava Cap Road between the two Altair Drive intersections.  The crew will be installing the treated water services and vaults from 7:00 AM to 5:00 PM with one lane open for traffic flow. Expect delays up to twenty minutes.  Electronic signage is being set up as well.

Wednesday, September 29, 2010

Construction / Traffic Update from NID as of 9/28/10

9/28/10
Traffic Update for NID’s Banner Cascade Pipeline Project Construction

Construction on NID’s Banner Cascade Pipeline project continues on Banner Mountain .  Construction is currently taking place on Banner Lava Cap Road between both Altair Drive intersections and on Lee Lane . Expect 20 minute delays while watching for construction signage and flaggers as they help safely direct traffic through the construction zones. 

 If you need further information, contact Hugh Gordon, Project Ombudsman, at (530) 263-4352 or email: Hugh-lu@att.net



Notices posted on the information boards:

Treated Water Pipe installation on

Banner Lava Cap Road

has resumed between the two
Altair Drive intersections.

EXPECT TRAFFIC DELAYS UP TO TWENTY MINUTES!
Flaggers will be on site to safely direct traffic. 
Emergency vehicles will be given immediate access.
If possible, use alternate routes. Thank you for being patient.


Banner Cascade Pipeline Project Construction Schedule 9/27/10 to 10/22/10
Madrone Forest Drive
  • Vault construction is complete.  Pipeline testing is underway.
  • Final asphalt paving will begin in October after the Overland route between the Airport and Madrone Forest Drive is complete.
  • Phase one of restoration, soil stabilization, will begin after the final pavement has been completed.  Phase two of restoration, vegetation replanting, will be scheduled shortly thereafter.
  • Please continue to drive slowly on the gravel roadway. 
Overland between Madrone Forest Drive and the airport: 
  • Installation of the 36” raw water pipeline on the Overland section is completed. Testing and general clean up has started.
  • Phase one of restoration has begun; soil stabilization of the slope is underway.  Phase two of restoration, vegetation replanting, will begin after paving on Madrone Forest Drive is complete.
Airport & Loma Rica Water Treatment Plant: 
·        Final clean-up along pipeline route is underway.
·        Loma Rica Water Treatment Plant structures being constructed.
Lee Lane: 
  • 48” raw water pipeline installation continues. The treated water pipeline will follow.  Flaggers will get you through the construction as quickly as safety allows.  Thank you for your patience.
  • Lee Lane residents are invited to join NID for an on the street meeting 9/29 at 6:00 PM at the intersection of Lee Lane and Climbing Way .  NID would like to share the current construction plan and have residents’ input to create a workable plan to continue construction until weather no longer permits.
Idaho Maryland Road, between Lee Lane and Banner Lava Cap Road : 
·        Pipeline installation will begin after Banner Lava Cap Road section is completed.  Expected start date is 10/4.
Banner Lava Cap Road, between Idaho Maryland Road and Wings of
     Moring Drive: 
  • Teichert’s first crew is installing the treated water pipeline on Banner Lava Cap Road between the two Altair Drives. 
  • Phase one of restoration, soil stabilization, will begin after the treated water pipeline installation has been completed.  Phase two of restoration, vegetation replanting, will be scheduled shortly thereafter.
Construction Scheduled to Begin in 2011
Wings of Morning Drive
Opalite Way
Red Dog Cross Road
Clipper Creek Siphon
Overland from Madrone Forest Drive to Red Gate Road
Red Gate Road
Banner Lava Cap Road to E. George Water Treatment Plant

Monday, September 20, 2010

NID Documents

NID has provided the following documents.  Read them with a grain of salt or maybe an entire shaker.

Fire Protection Plan

Ombudsman Job Description

Particulate Emission Plan (appropriately titled emission not control)

Speeding trucks

 I want to mention that there have been a few times on Idaho-Maryland that the trucks coming up ( and going down) are speeding and I have had to honk at them to slow down.  I think they are trying to get speed up in the low part so they don’t slow way down when the hill gets steeper on the way up.  On the way down they are loaded and would have a hard time stopping.  Regardless, they are going too fast and should watch the speed limits. 

Saturday, September 18, 2010

Banner Cascade Pipeline Project 24 Hour Contact Information

This information provided to us by NID


If you have questions or concerns, please contact us.
We’d like you to be informed on our plans for the project.

Hugh Gordon
NID Ombudsman
(530) 263-4352

Sarah Rohde
NID Information Coordinator and Ombudsman
(530) 913-0896

Brian Powell
NID Project Manager
(530) 271-6869 Office
(530) 277-8262 Cell

Brian Roth
Teichert Project Manager
(916) 825-3091
Emergency (800) 287-7383
Crime Prevention (913) 452-3535

Emergencies, 911
Nevada County Sheriff, (530) 265-7880
Nevada County Consolidated Fire Department, (530) 273-3158