Construction on NID’s Banner Cascade Pipeline project continues on Banner Mountain during good weather conditions. Watch for construction signage and flaggers as they help safely direct traffic through the construction zones. Installation of the 10 inch treated water pipeline and the 48 inch raw water tie-in on Idaho Maryland Road will resume Tuesday, 4/26, between Banner Lava Cap Road and Lee Lane. If possible, use Banner Lava Cap Road as an alternate route to avoid construction delays up to twenty minutes.
Logging activities will resume Thursday, 4/28, on Wings of Morning Drive between Clipper Creek Road and Banner Lava Cap Road. Detour signage will be set up to direct traffic through the construction zone. No delays are anticipated at this time.
Vault installation, joint sealing, and testing will be scheduled on Idaho Maryland Road and Banner Lava Cap Road, weather dependent. Traffic will be limited to one lane while construction activities are underway; expect minimal delays.
If you need further information, contact Hugh Gordon, Project Ombudsman, at (530) 263-4352 or email: Hugh-lu@att.net
Notices:
Installation of the treated water pipeline on Idaho Maryland Road
is underway near the intersection with St. Ledger’s Forest Road.
Work will proceed toward Lee Lane, where the raw water tie-in is being installed. Use Banner Lava Cap Road as an alternate route to avoid the construction.
Flaggers will safely direct traffic through the construction zones. Emergency vehicles will be given immediate access. Thank you for being patient.
Logging has resumed on Wings of Morning Drive between Clipper Creek Road and Banner Lava Cap Road. Traffic detours will be set up allowing residents to avoid driving through the construction zone. Watch for signage; no delays are anticipated at this time.
Flaggers will safely direct traffic through the construction zones. Emergency vehicles will be given immediate access. Thank you for being patient.
Vault installation, joint sealing, and testing will be underway on
Idaho Maryland Road and Banner Lava Cap Road, weather dependent. Traffic will be limited to one lane with delays up to twenty minutes expected.
Flaggers will safely direct traffic through the construction zones. Emergency vehicles will be given immediate access. Thank you for being patient.
Banner Cascade Pipeline Project Construction Schedule
4/25/11 to 5/20/11
Installation of the treated water pipeline on Idaho Maryland Road will resume Tuesday, 4/26, near the intersection with St. Ledger’s Forest Road. Work will proceed toward Lee Lane where the raw water tie-in is being installed; expect delays up to twenty minutes. Use Banner Lava Cap Road as an alternate route to avoid the construction.
Logging activity will resume on Wings of Morning Drive Thursday, 4/28, between Clipper Creek Road and Banner Lava Cap Road. Detour signage will be set up to direct traffic through the construction zone; no delays are anticipated at this time. NID inspectors will be on site full-time to ensure Robinson Enterprises’ employees stay within the TCE and to take care of any unforeseen events should they occur.
■ Banner Lava Cap Rd to E. George Water Treatment Plant: To be
determined.
■ Red Gate Road: To be determined.
■ Overland from Madrone Forest Drive to Red Gate Road: To be determined.
■ Madrone Forest Drive: Restoration to be scheduled for the fall of 2011.
■ Overland between Madrone Forest Drive and the airport: Construction and
restoration is completed.
■ Airport and Loma Rica Water Treatment Plant: Construction is ongoing;
however, activities should not affect nearby residents. Restoration to be
scheduled for the fall of 2011.
■ Lee Lane:
· Raw water tie-in to Idaho Maryland Road to be installed Tuesday, 4/26.
· The final lift of pavement and testing of the raw and treated water pipelines will resume in the spring.
· Restoration to be scheduled for fall 2011.
■ Idaho Maryland Road, between Lee Lane and Banner Lava Cap Road:
· Installation of the treated water pipeline and the raw water tie-in to Lee Lane will resume Tuesday, 4/26. See opening paragraph for details.
· Vault installation, joint sealing, and testing of the 48” raw water pipeline will be scheduled, weather dependent. Flaggers will be onsite to direct traffic; minimal delays are expected.
· The final lift of pavement will be installed in spring of 2011.
· Phase two of restoration, tree and vegetation replanting, will be scheduled for the fall of 2011.
■ Banner Lava Cap Road, between Idaho Maryland Road and Wings of
Morning Drive:
· Vault installation, joint sealing, and testing of the pipeline will be scheduled, weather dependent. Flaggers will be onsite to direct traffic; minimal delays are expected.
■ Wings of Morning Drive:
· Logging will resume Thursday, 4/28, between Clipper Creek Road and Banner Lava Cap Road. See opening paragraph for details.
■ Opalite Way/Snow Mtn. Flow Control/Overland: Logging will resume,
weather dependent.
■Red Dog Cross Road, Lola’s Echo Road, and Oak Ridge Road: Logging to
begin in May.