Wednesday, June 15, 2011

6/14/11 Traffic Update for NID’s Banner Cascade Pipeline Project Construction

Construction on NID’s Banner Cascade Pipeline project continues on Banner Mountain during good weather conditions.  Watch for construction signage and flaggers as they help safely direct traffic through the following construction zones. Raw water pipeline installation continues along the east end of Wings of Morning Drive.  Construction equipment and trucks will enter and exit Wings of Morning Drive from both ends from now until the project is completed.  Turnouts are available along the alignment route allowing for passing residential traffic.

Final work on vaults is scheduled on Banner Lava Cap Road, between Idaho Maryland Road and Wings of Morning Drive, weather dependent. Traffic will be limited to one lane while construction activities are underway.  Minimal delays are expected, however they may be up to twenty minutes in duration.

General clean up on Lee Lane is underway. Minimal delays are expected, however they may be up to twenty minutes in duration.

If you need further information, contact Hugh Gordon, Project Ombudsman, at (530) 263-4352 begin_of_the_skype_highlighting            (530) 263-4352      end_of_the_skype_highlighting, email: Hugh-lu@att.net, or visit our webpage at www.nidbannercascade.com.

Notices:
Residents that live along the pipeline alignment, or travel through the construction zone, and interested community members are invited to attend an open forum meeting Thursday, June 16th, from 6:30pm to 8:30pm in the NID Boardroom.  NID and Teichert personnel will be present to address concerns that may be arising and answer questions about the project.

Raw water pipeline installation will continue along the east end of
Wings of Morning Drive.  Construction equipment and trucks will
enter and exit Wings of Morning Drive from both ends until the
project is completed.  Turnouts are available along the alignment
route allowing for passing residential traffic.

Final work on vaults is scheduled on Banner Lava Cap Road, between Idaho Maryland Road and Wings of Morning Drive, weather dependent. Traffic will be limited to one lane while construction activities are underway.  Minimal delays are expected, however they may be
up to twenty minutes in duration.

General clean up on Lee Lane is underway. Minimal delays are expected, however they may be up to twenty minutes in duration.

Flaggers will safely direct traffic through the construction zones. Emergency vehicles will be given immediate access. Thank you for being patient.

Banner Cascade Pipeline Project Construction Schedule
6/13/11 to 7/8/11

Banner Lava Cap Rd to E. George WTP: To be determined.
Red Gate Road: To be determined.
Overland from Madrone Forest Drive to Red Gate Road: To be determined.
Madrone Forest Drive: Restoration to be scheduled for the fall of 2011.
Overland between Madrone Forest Drive and the airport: Construction and
restoration are completed.
Airport and Loma Rica Water Treatment Plant: Construction is ongoing;
however, activities should not affect nearby residents. Restoration to be
scheduled for the fall of 2011.
Lee Lane:
·        Treated water is now available for residents adjacent to the alignment; contact NID Customer Service at 530-273-6185 begin_of_the_skype_highlighting            530-273-6185      end_of_the_skype_highlighting for connection information. 
·        General cleanup will continue this week, expect minimal delays.
·        Raw water pipeline installation across SWROA lot 3 toward the airport and testing of the raw water pipeline and will begin soon. 
·        The final lift of pavement will be scheduled for July 2011.
·        Restoration scheduled for fall 2011.
Idaho Maryland Road, between Lee Lane and Banner Lava Cap Road:
·        Treated water is now available for residents adjacent to the alignment; contact NID Customer Service at 530-273-6185 begin_of_the_skype_highlighting            530-273-6185      end_of_the_skype_highlighting for connection information. 
·        Testing of the raw water pipeline will begin soon. 
·        The final lift of pavement will be scheduled for July 2011.
·        Restoration scheduled for fall of 2011.
Banner Lava Cap Road, between Idaho Maryland Road and Wings of
Morning Drive:
·        Final work on vaults and testing of the raw water pipe will continue this week. 
·        The final lift of pavement will be scheduled for July 2011.
·        Restoration scheduled for fall of 2011.
Wings of Morning Drive:
·        Raw water pipeline installation continues along the east end of Wings of Morning Drive.  Construction equipment and trucks will enter and exit Wings of Morning Drive from both ends from now until the project is completed.  Turnouts are available along the alignment route allowing for passing residential traffic.
Opalite Way/Snow Mtn. Flow Control/Overland:
·        Excavation for building foundation has started.
Red Dog Cross Road, Lola’s Echo Road, and Oak Ridge Road:
·        Logging activity is complete.  Stump grinding will soon follow.   Pipeline installation is scheduled for July.  Advanced notice of the construction will be given.  

No comments: