Construction on NID’s Banner Cascade Pipeline project continues on Banner Mountain during good weather conditions. Watch for construction signage and flaggers as they help safely direct traffic through the construction zones. Appurtenance installation continues on Idaho Maryland Road near St. Ledger Forest Road with short delays. Use Banner Lava Cap Road as an alternate route to avoid the construction, if possible.
Detour signage is set up to safely direct residential traffic through the construction zone in the Wings of Morning Drive neighborhood. The raw water pipeline installation is progressing Overland from Opalite Way and south on Wings of Morning Drive toward Sesame Street. No delays are anticipated at this time.
Logging activity will begin on Oak Ridge Drive and Lola’s Echo Road starting Friday, 5/20, or Monday, 5/23, with minimal delays, weather dependent. Watch for construction signage and flaggers as they help safely direct traffic through the construction zones.
Vault installation, joint sealing, and testing will be scheduled on Idaho Maryland Road and Banner Lava Cap Road, weather dependent. Traffic will be limited to one lane while construction activities are underway; expect minimal delays.
If you need further information, contact Hugh Gordon, Project Ombudsman, at (530) 263-4352 or email: Hugh-lu@att.net
Notices:
Appurtenance installation will continue on Idaho Maryland Road near
St. Ledger Forest Road with short delays. Use Banner Lava Cap Road as an alternate route to avoid the construction, if possible.
Vault installation, joint sealing, and testing will be underway on
Idaho Maryland Road and Banner Lava Cap Road, weather dependent. Traffic will be limited to one lane with delays up to twenty minutes.
Flaggers will safely direct traffic through the construction zones. Emergency vehicles will be given immediate access. Thank you for being patient.
Detour signage is set up to safely direct residential traffic through the construction zone in the Wings of Morning Drive neighborhood. The raw water pipeline installation is progressing Overland from Opalite Way and south on Wings of Morning Drive toward Sesame Street.
No delays are anticipated at this time.
Logging activity will begin on Oak Ridge Drive and Lola’s Echo Road starting Friday, 5/20, or Monday, 5/23, with minimal delays,
weather dependent.
Flaggers will safely direct traffic through the construction zones. Emergency vehicles will be given immediate access. Thank you for being patient.
Banner Cascade Pipeline Project Construction Schedule
5/16/11 to 6/10/11
■ Banner Lava Cap Rd to E. George WTP: To be determined.
■ Red Gate Road: To be determined.
■ Overland from Madrone Forest Drive to Red Gate Road: To be determined.
■ Madrone Forest Drive: Restoration to be scheduled for the fall of 2011.
■ Overland between Madrone Forest Drive and the airport: Construction and
restoration is completed.
■ Airport and Loma Rica Water Treatment Plant: Construction is ongoing;
however, activities should not affect nearby residents. Restoration to be
scheduled for the fall of 2011.
■ Lee Lane:
· Testing of the raw and treated water pipelines and completion of the vaults will begin soon with minimal delays. Restoration scheduled for fall 2011.
· The final lift of pavement is scheduled for June or July 2011.
■ Idaho Maryland Road, between Lee Lane and Banner Lava Cap Road:
· Appurtenance installation continues near St. Ledger Forest Road with short delays. Use Banner Lava Cap Road as an alternate route to avoid the construction, if possible.
· Vault installation, joint sealing, and testing of the 48” raw water pipeline will be scheduled, weather dependent. Flaggers will be onsite to direct traffic; minimal delays are expected.
· The final lift of pavement is scheduled for June or July 2011.
· Phase two of restoration, tree and vegetation replanting, will be scheduled for the fall of 2011.
■ Banner Lava Cap Road, between Idaho Maryland Road and Wings of
Morning Drive:
· Vault installation, joint sealing, and testing of the pipeline will be scheduled, weather dependent. Flaggers will be onsite to direct traffic; minimal delays are expected.
■ Wings of Morning Drive:
· Raw water pipeline installation continues across the Overland section and south onto Wings of Morning Drive. A detour route is set up for the Wings of Morning Drive neighborhood; no traffic delays are anticipated.
■ Opalite Way/Snow Mtn. Flow Control/Overland:
· Logging complete; raw water pipeline installation continues Overland progressing toward Wings of Morning Drive.
■Red Dog Cross Road, Lola’s Echo Road, and Oak Ridge Road:
· Logging activity will begin on Oak Ridge Drive and Lola’s Echo Road starting Friday, 5/20, or Monday, 5/23, with minimal delays, weather dependent.