Construction on NID’s Banner Cascade Pipeline project continues on Banner Mountain. Joint sealing and testing will be underway inside the pipeline this week on Idaho Maryland Road and Banner Lava Cap Road; traffic will be limited to one lane with minimal delays expected. Watch for construction signage and flaggers as they help safely direct traffic through the construction zones.
If you need further information, contact Hugh Gordon, Project Ombudsman, at (530) 263-4352 or email: Hugh-lu@att.net
Notice:
Regular construction activities will resume
when weather conditions improve.
Work inside the pipeline and maintenance
will continue over the winter months.
Traffic may be limited to one lane with minimal delays expected.
Flaggers will safely direct traffic through the construction zones.
Emergency vehicles will be given immediate access.
Thank you for being patient.
Banner Cascade Pipeline Project Construction Schedule 1/5/11 to 1/28/11
■ Madrone Forest Drive:
· Finalizing culvert installation; no traffic delays are expected.
· Final clean-up is in progress.
· Phase one of restoration, soil stabilization, is completed; the contractor will maintain slopes through the winter. Phase two of restoration, tree and vegetation replanting, will be scheduled for the fall of 2011.
■ Overland between Madrone Forest Drive and the airport:
· Phase one of restoration, soil stabilization, is completed; the contractor will maintain slopes through the winter. Phase two of restoration, vegetation replanting, will be scheduled for January.
■ Airport & Loma Rica Water Treatment Plant:
· Saturday work from 7:00 AM to 5:00 PM is possible; no traffic delays are expected.
· Final clean-up along pipeline route is underway.
· Loma Rica Water Treatment Plant structures being constructed.
■ Lee Lane:
· The final lift of pavement and testing of the 48” raw water pipeline will resume in the spring.
· Tie-in to Idaho Maryland Road to be scheduled.
■ Idaho Maryland Road, between Lee Lane and Banner Lava Cap Road:
· Joint sealing and testing of the 48” raw water pipeline will begin. Flaggers will be onsite to direct traffic; minimal delays are expected.
· Curb installation to be scheduled when weather conditions improve; the final lift of pavement will be installed in spring of 2011.
· Installation of the treated water pipeline is on hold until weather conditions to improve.
· Tie-in to Lee Lane to be scheduled.
· Phase one of restoration, soil stabilization, is underway; the contractor will maintain slopes through the winter. Phase two of restoration, tree and vegetation replanting, will be scheduled for the fall of 2011.
■ Banner Lava Cap Road, between Idaho Maryland Road and Wings of Morning
Drive:
- Joint sealing and testing of the 48” raw water pipeline will begin. Flaggers will be onsite to direct traffic; minimal delays are expected.
· Curb installation completed. The final lift of pavement will be installed in spring of 2011.
· The contractor is waiting for weather conditions to improve in order to start on vault construction.
Construction Scheduled to Begin in 2011
■ Wings of Morning Drive
■ Opalite Way
■ Red Dog Cross Road
■ Clipper Creek Siphon
■ Overland from Madrone Forest Drive to Red Gate Road
■ Red Gate Road
■ Banner Lava Cap Road