Banner Cascade Pipeline Project Construction Schedule 9/13/10 to 10/8/10


This information provided to us by NID
Madrone Forest Drive: 
  • Final asphalt paving will begin in October after the Overland route, vault construction, and testing on Madrone Forest Drive are complete. Vegetation restoration will begin after paving is complete. Please continue to drive slowly on the gravel roadway.  We appreciate your continued patience with the construction process. 

Overland between Madrone Forest Drive and the airport: 
  • Teichert’s first crew is now installing the 36” raw water pipeline on the Overland section.

Airport & Loma Rica Water Treatment Plant: 
·        Final clean-up along pipeline route is underway.
·        Loma Rica Water Treatment Plant structures being constructed.

Lee Lane: 
  • Teichert’s second crew continues work on the 48” raw water pipeline installation. The treated water pipeline will follow.  Flaggers will get you through the construction as quickly as safety allows.  Thank you for your patience.

Idaho Maryland Road, between Lee Lane and Banner Lava Cap Road: 
·        Pipeline installation will begin after Banner Lava Cap Road section is completed.  Expected start date is 10/4.

Banner Lava Cap Road, between Idaho Maryland Road and Wings of
     Moring Drive: 
  • In October the first crew will return to install the treated water pipeline between the two Altair Drives. 

Construction Scheduled to Begin in 2011
Wings of Morning Drive
Opalite Way
Red Dog Cross Road
Clipper Creek Siphon
Overland from Madrone Forest Drive to Red Gate Road
Red Gate Road
Banner Lava Cap Road to E. George Water Treatment Plant